Constitution Hill

The Project: Constitution Hill safety improvements

Client: DIER

Value: $7.9M

Construction Period: November 2008 - July 2009

Location: Constitution Hill, Midland Highway

The project included:

  • Surface and subsurface drainage
  • Stormwater works including major box culvert extension
  • Supply and placement of pavement sub base,base material and bituminous surfacing
  • Installation of tensioned wire rope safety barrier and W beam safety barrier including back to back rail with skid rail
  • Supply and installation of rock filled gabions
  • Modification to a property access and fencing.