The Project: Lyell Highway - Murphy’s Flats to Molesworth Road
Client: DIER
Value: $3.7M
Construction Period: Nov 2008 - Dec 2009
Location: Lyell Highway.
The project included:
- Clearing and grubbing;
- Earthworks;
- Surface and subsoil drainage;
- Stormwater works including box culverts crossing the highway;
- Supply and placement of pavement sub base, base and verge material;
- Supply and placement of bituminous surfacing;
- Installation of traffic facilities including pavement marking and signs;
- Modification to property accesses and fencing;
- Minor concrete works;
- Protection of environmentally significant sites and environmental management;
- Traffic management;
- Topsoiling and hydromulching;
- Sundry minor works.